Oct 02 2006

Kitchen – Week 7, day 1

Published by under The new kitchen

We’re into week 7 of the kitchen renovation, and today was all about detail work and flooring. Specifically, trim and tiles. The most rewarding part about today’s work was the installation of the trim that Randye spent six hours stripping the paint from and sanding the other weekend. She used copious amounts of caustic paint [...]

No responses yet

Sep 30 2006

Kitchen – Week 6, day 5

Published by under The new kitchen

Yay for some real, visible progress! The columns have been trimmed out and they look fabulous. (I think Paul even offered to hug the foreman he was so happy with them.) It also turns out they aren’t entirely decorative: there’s a joist directly below the island in the basement, and the columns are made of [...]

One response so far

Sep 28 2006

Kitchen – Week 6, day 4

Published by under The new kitchen

Lots of detail work pushing the finishing side of things today. The crew started priming the wood sub-flooring so that it wouldn’t absorb the adhesive for the floor tiles. They also tidied up some things around the cabinets and started the wood trim on the island. And behold, we have the start to our columns! [...]

2 responses so far

Sep 27 2006

Kitchen – Week 6, day 3

Published by under The new kitchen

A whole lot more of not a lot to tell. Some minor cabinet progress, more plaster tweaks and a start to filling cracks and seams on the plywood subfloor for a smooth installation of the floor tile. Randye spent the day playing phone tag with the cabinet guy to work out some remaining minor issues. [...]

One response so far

Sep 26 2006

Kitchen – Week 6, day 2

Published by under The new kitchen

There was no spectacular progress today that can be noted. The guys fixed some nagging fit and hinge issues with the cabinets, reviewed how things would fit together with Randye and shored up some of yesterday’s work. We also discussed the issue of the bathroom floor with the contractors. It seems there’s a bit of [...]

2 responses so far

Sep 25 2006

Kitchen – Week 6, day 1

Published by under The new kitchen

A busy day in the kitchen today, as the contractors focused on installing cabinetry. They also sanded down the rest of the plaster on the walls. The cabinet rep. came by to talk to Randye about a few details that came up with what was delivered and other than that, it was all about installation. [...]

2 responses so far

Sep 24 2006

Kitchen – End of week 5

Published by under The new kitchen

While Paul was rowing in another regatta on Saturday, I stayed home to oversee the kitchen’s progress. The foreman and another guy came by on Saturday as previously promised. They spent a few hours inspecting and opening the various cabinetry boxes and measuring things out to ensure installation moves as smoothly as possible. A few [...]

No responses yet

Sep 22 2006

Kitchen – Week 5, day 5

Published by under The new kitchen

Nothing to report today. The contractors were away on another project and promise to be here tomorrow.

No responses yet

Sep 21 2006

Kitchen – Week 5, day 4

Published by under The new kitchen

It was absolutely nuts today, but in a good way. To start, the plumber came by because he had some free time and attached the heating pipes to the existing radiators so we could have heat. Eventually he’ll attach the new radiator and pipes, but we’re good for now. He came by because he had [...]

One response so far

Sep 20 2006

Kitchen – Week 5, day 3

Published by under The new kitchen

Another busy day with the drywall/plasterers. One of the regular contractors came by first thing this morning to uncover the part of the chimney that was covered yesterday. He also fixed an issue in the pantry nook where some of the drywall was sticking out and would have hampered installation of the pantry cabinetry and [...]

No responses yet

« Newer Entries - Older Entries »